Over 2,500 Km of roads constructed under Bharatmala in Andhra Pradesh

      Comments Off on Over 2,500 Km of roads constructed under Bharatmala in Andhra Pradesh




NEW DELHI: Under Bharatmala project, about 2,520 Km of roads amounting to Rs 44 thousandcrore have been envisaged in the State of Andhra Pradesh. Details of Bharatmala Roads is as under:

  1. Under Economic Corridor
 Length 

(in Km.)

Status
Madanapalli  –Pileru  Section of NH-7154.86DPR in progress
Pileru – Cherlopalli Section of NH-7150.94DPR in progress
Renigunta to Poyya section of NH-7155.2DPR in progress
Kadapa – Renigunta (NH-40) (Chennai – Puttur – Kadapa – Nandyal – Kurnool)138DPR in progress
AP / KN Border – Alur – Adoni section of Hasan – Raichur83.89DPR in progress
Visakhapatnam – Raipur Section:

Developmental works of NH-26 from Ondarangi –  Vizianagaramin  the state of Andhra Pradesh (Visakhapatnam – Raipur section).

70DPR in progress
Sub Total247.00 
B. Under Inter Corridor Routes  
Mydukur – Badvel section of NH – 6741DPR in progress
Badvel – Nellore106.77DPR in progress
Sub Total147.77 
C. Under NHAI / NH (O)  
DPR for upgradation of the highway starting from junction with NH-44 at Anantapur – Giddalur of NH 544D in the State of Andhra Pradesh to Two / Four lane with paved shoulder configuration (Pkg-I & II)139.00DPR in progress
Two lane with paved shoulder of Anantapur – Giddalur of NH 544D (Pkg-III) (Bugga to Kaipa)57.400Bids Invited
Two lane with paved shoulder of Anantapur – Giddalur of NH 544D (Pkg-IV) (Kaipa to Giddalur)77.569Bids Invited
DPR for upgradation of the highway starting Giddalur to Guntur of NH 544D (Vinukonda – Guntur) in the State of Andhra Pradesh to Two / Four lane with paved shoulder configuration83.00DPR in progress
DPR for Upgradation of Kurnool – Dornala section of NH-340C to Two/Four lane with paved shoulder configuration124.15DPR in progress
Sub Total481.119 
D. Ring Roads  
6-laning of Chilakaluripet Bypass on NH-16 under NHDP Phase-V on BOT(Toll)16.384DPR in progress
Feasibility Study Report for Construction of Outer Ring Road around Vijayawada – Guntur – Tenali Urban Agglomeration in the States of Andhra Pradesh on Green Field Alignment under NHDP Phase-VII189DPR in progress
Sub Total205.384 
E Costal Roads  
Kathipudi – Ongole stretch of NH-216 (2l+PS/4L)363Work in progress in 9 packages
Sub Total363 
F  Residual Works in NHDP  
Davulapally – Markapuram – Vagampalli – Dornala and Penchalkona – Yerpedu section of NH 565 (2L+PS) (Implemented in 4 packages)287Work completed
Mydukur – Nellore section of NH-67 (Implemented in 3 packages) (2L+PS)149.5Work completed
Ibrahimpatnam – Chandragudem and Chandragudem-A.P Telangana border section of NH 221 (Implemented in 2 packages) (2L+PS)70.3Work completed
Dornala – Penchalakona section of Nh-565 (2L+PS)42Work in progress
Karnataka/AP Border-Gooty section of NH-67 (4L)57Work in progress
Nagarjunsagar Dam- Davulpally section of NH-56547DPR complete
Davulpally reserve forest section of NH-56522DPR in progress
Sub Total674.8 
G Connectivity of Backward districts and Religious and Tourist centres  
Malkangiri on NH 326-  Chintapalle-Naripattanam – Waddai – Chodavaram-Sabbavaram&Narsipatnam – Tuni section280DPR in progress
Route starting from NH-565 Gotlagattu – Podile – Uppalapadu – Chimakurti – Ongole on NH-16.107DPR in progress
Sub Total387